PIT-INSP-05 Pipes
- Installation/equipment identification data: Pipes
- Inspection Type:
Technical inspection in use
Technical inspection in use after repair
Technical inspection to authorize operation
- Inspection/testing/verification methods according to:
3.1 inspection procedure: PIT-INSP-05
3.2 Technical prescription: PT C 10 / 2010
- Inspection/verification/testing facilities and equipment specific to each type of installation/equipment provided by the holder/maintainer (metrologically verified measurement and monitoring equipment)
- Inspector PG-INSP-16 safety requirements, SSM and SU specific requirements
- Inspection activities:
- Preliminary checks
6.1. Technical mounting documentation, registers, etc.
- Technical checks
6.2. External check
6.3. Checking the safety devices/safety valves
6.4. Hydraulic pressure test/ pneumatic pressure test
6.5. Sealing test
- Preparation of the inspection report