PIT-INSP-03 Containers
- Installation/equipment identification data: Containers
- Inspection Type:
Technical inspection in use
Technical inspection in use after repair
Technical inspection to authorize operation
- Inspection/test/verification methods according to:
3.1 PIT-INSP-03 inspection procedure
3.2 Technical prescription: PT C 4-2010, PT C 12-2003
- Inspection/verification/testing facilities and equipment specific to each type of installation/equipment provided by the holder/maintainer (metrologically verified measurement and monitoring equipment)
- Inspector PG-INSP-16 safety requirements, SSM and SU specific requirements
- Inspection activities:
- Preliminary checks
6.1. Technical documentation, registers, etc.
- Technical checks
6.2. Internal inspection – internal check
6.3. Internal inspection – external check
6.4. Checking safety devices/safety valves
6.5. Hydraulic pressure test
6.6. Pneumatic sealing test
6.7 Check the vacuum degree
- Preparation of the inspection report