PIT-INSP-02 Boilers
- Installation/equipment identification data: Boiler
- Inspection Type:
Technical inspection in use
Technical inspection in use after repair
Technical inspection to authorize operation
- Inspection/testing/verification methods:
3.1 Inspection procedure: PIT-INSP-02
3.2 Technical prescription: PT C9/2010, PT C11/2010, PT C7/2010
- Inspection/verification/testing facilities and equipment specific to each type of installation/equipment provided by the holder/maintainer (metrologically verified measurement and monitoring equipment)
- Inspector safety requirements: PG-INSP-16, SSM and SU specific requirements
- Inspection activities:
- Preliminary checks
6.1. Technical documentation, mandatory installation notice, registers, etc.
- Technical checks
6.2. Internal inspection – internal check
6.3. Internal inspection – external check
6.4. Checking safety devices/safety valves
6.5. Hydraulic pressure test
6.6. Hot test
7. Preparation of the inspection report.